State Department of Education |
|
|
|
|
Capital Plan Five Year Plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
As of 3/25/2022 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
System: |
Elba City |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$240,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
This amount include loan payment of 107,000 to Schneider Electric, annual insurance of 77,000 and purchase of HVAC units of 60,000. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Land Improvements |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$210,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Parking lot and road improvements on campus. Football reserve parking and bus loading road area between both schools. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
Land Improvements |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2023 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$500,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
High School loading dock road, Career Tech parking lot, football track, front parking lot and loading, and student parking lot. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Land Improvements |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$120,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Erosion issues on the grounds of Elba City Schools. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
Land Improvements |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2023 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$110,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Elementary parking lot, front entrance loading, and side road. Elementary walking path and outside basketball court. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
6 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
Renovations |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$20,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Replace carpet with tile. Continue to paint the classrooms and hallways. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
7 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replaced at High School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacment at Elementary School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
9 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
Renovations |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2023 |
|
Project Budget: |
$15,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Continue to paint classrooms and hallways. Replace carpet with tile. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
Renovations |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2023 |
|
Projected Completion Year: |
2023 |
|
Project Budget: |
$15,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Replace carpet with tile and continue to paint the hallways and classrooms. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
11 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Information Technology |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2023 |
|
Project Budget: |
$25,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Purchase of technology |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
12 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Information Technology |
|
Project Rationale: |
Educational Programs |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$50,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Funding for technology equipment for the classrooms. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
13 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2022 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at high school |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
14 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2023 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
|
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at High School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
15 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2023 |
|
Projected Completion Year: |
2024 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
|
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at High School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
16 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2024 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
|
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacment at High School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
17 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2023 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at Elementary School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
18 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2023 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
|
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at Elementary School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
19 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2023 |
|
Projected Completion Year: |
2024 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at Elementary School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
20 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
HVAC Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2024 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$60,000.00 |
|
Project Completion Date: |
|
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/5 of HVAC replacement at Elementary School |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
21 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
Roofing Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$100,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/2 roof replacement at Elba High |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
22 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Information Technology |
|
Project Rationale: |
Educational Programs |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2025 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$25,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Purchase of technology for the classrooms. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
23 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
Roofing Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$100,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/2 roof replacement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
24 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba Elementary School |
|
Project Classification: |
Roofing Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2023 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$100,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/2 roof replacement |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
25 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Roofing Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2026 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$20,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
roof replacement at central office |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
26 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba High School |
|
Project Classification: |
Roofing Only |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
0000 |
|
Project Budget: |
$100,000.00 |
|
Project Completion Date: |
/ |
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
1/2 roof replacement at Elba High |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Priority: |
27 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name: |
Elba City Board Of Education |
|
Project Classification: |
Land Improvements |
|
Project Rationale: |
Facility Assessment |
|
Project Substandard Classroom: |
NA |
|
Primary Funding Source: |
Funding Source Unknown |
|
Funding Year: |
2022 |
|
Projected Completion Year: |
2024 |
|
Project Budget: |
$175,000.00 |
|
Project Completion Date: |
|
|
Other Rationale: |
|
|
Other Substandard Classroom: |
|
|
Project Description: |
Paving central office parking lot and road as well as the bus shop. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Page 1 of 1 |